Wednesday, January 27, 2010

Excavation COMPLETE (Jan 27th 2010)

Well today we finally got some progress on our land. The site has been cut and filled, and is now ready for the next stage to begin. The slab is to be poured by Monday February 8th, then things will roll on from there. Finallly things are starting after such a very long wait. A very happy day today. Here are some photos taken today. CLICK ON EACH PHOTO FOR LARGER VIEW







Nice new level surface.















Oh yeah, Molly says lets move in already!!








































Friday, January 15, 2010

Excavation begins 3rd February 2010

We have been notified that excavting will begin around 3rd February 2010. Surveyors have already pegged out site. Land will be mowed again over this weekend in preparation for earthworks. So finally some movement after all this time. Will keep this site updated regularly once they begin. So keep your eyes open for new pics arriving from February onwards.