Tuesday, March 23, 2010
Gyprock Sheeting 99% Complete
2nd Bedroom
Kitchen Heatshield Lining
Dining / Family
Entry showing nib wall to right for picture recess
Monday, March 22, 2010
Gyprock to Walls and Ceiling Started
Thursday, March 18, 2010
Colorbond Roof Complete ! Eave sheeting has now started.
Wednesday, March 17, 2010
Tuesday, March 16, 2010
Colorbond Roof and Internal Plumbing Near Completion
Friday, March 12, 2010
Wednesday, March 10, 2010
Front Brickwork Completed
Tuesday, March 9, 2010
Front Brickwork and Roof Batterns Begin
Friday, March 5, 2010
Brickwork to Rear Wall and West Side
Thursday, March 4, 2010
Brickwork Continues
Brickwork continued today completing around dining and family areas. Alfresco walls have also begun, just need the other window to finish. Bricklayers doing a great job, very neat finish, which is hard to come by. The Monte Carlo is slowing showing itself day by day, and we can't wait until lockup stage, which won't be to far away.
Tuesday, March 2, 2010
Windows Installed Bricklayers Starting
Subscribe to:
Posts (Atom)