Tuesday, February 16, 2010

Trusses Installed

Today the trusses were installed. Also the frame was plumbed and braced and bath hob was also installed. They are continuing to finish the bracing, then windows and brickwork will begin. Things moving alot faster than expected.




















































Friday, February 12, 2010

Wall Frames Up

Today all the wall frames have been put up. So it won't be long now and the trusses will be up also.
Things are moving quickly so far.











View of external wall to family/dining and garage. Notice step out in wall for where family TV will be located.

Wednesday, February 10, 2010

Frames and Trusses Delivered

Today the frames and trusses were delivered to the site. Also the electrical metre box was installed, and dirt was levelled on right side of block. Everything so far so good.










Electrical metre box installed to right of garage slab.

Tuesday, February 9, 2010

SLAB POURED

Today was a step forward with the slab finally being poured. Recycled water pipes are now to be installed along with pit, then frames and trusses will go up afterwards. So slowly but surely things are progressing. The master bedroom is to the left, then patio with double garage to the right. Click on any image on this site to ENLARGE any photos you want to look at.








Just a little water left from some light drizzle in the afternoon, but nothing excessive. Just need a few good days of sun now, which is expected so all is looking good.

Saturday, February 6, 2010

Waffle Pods / Steel Installed


The waffle pods and steel are now complete, and slab is ready to be poured on Monday weather permitting, so things are moving steadily so far.

Friday, February 5, 2010

Concrete Footings / Sand Bed Complete

Today the concrete piers were done and the packing sand was laid. One step closer to slab being poured.

Thursday, February 4, 2010

Formwork Begins


Today the formwork for slab had begun even though it poured rain early in the morning, they still managed to get most of the outer formwork done. Waffle pods and temporary fence also arrived.

Wednesday, February 3, 2010

Plumbing Completed


Today plumbing was installed. Drilling of piers and preparation of formwork for slab due to begin Thursday February 4th, but maybe delayed due to possible rain over the coming days. Slab booked in to be poured Monday 8th February.