Tuesday, February 16, 2010
Trusses Installed
Today the trusses were installed. Also the frame was plumbed and braced and bath hob was also installed. They are continuing to finish the bracing, then windows and brickwork will begin. Things moving alot faster than expected.
Friday, February 12, 2010
Wall Frames Up
Wednesday, February 10, 2010
Frames and Trusses Delivered
Tuesday, February 9, 2010
SLAB POURED
Today was a step forward with the slab finally being poured. Recycled water pipes are now to be installed along with pit, then frames and trusses will go up afterwards. So slowly but surely things are progressing. The master bedroom is to the left, then patio with double garage to the right. Click on any image on this site to ENLARGE any photos you want to look at.
Just a little water left from some light drizzle in the afternoon, but nothing excessive. Just need a few good days of sun now, which is expected so all is looking good.
Just a little water left from some light drizzle in the afternoon, but nothing excessive. Just need a few good days of sun now, which is expected so all is looking good.
Saturday, February 6, 2010
Waffle Pods / Steel Installed
Friday, February 5, 2010
Concrete Footings / Sand Bed Complete
Thursday, February 4, 2010
Formwork Begins
Wednesday, February 3, 2010
Plumbing Completed
Subscribe to:
Posts (Atom)